On 03/19/2018 08:45 AM, Jordan, Robin L wrote:

Current Dev Position: YP 2.5 M3 final close out.

Next Deadline: YP 2.5 M3 cut off was 2/19/18

*** FEATURE FREEZE for 2.5 has passed ***

 

SWAT lead is currently Ross.

SWAT team rotation: Armin -> Ross on March 23, 2018

SWAT team rotation: Ross -> Juro on March 30, 2018

https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team

 

Key Status/Updates:

 

Planned upcoming dot releases:

YP 2.3.4 (Pyro) will be built after 2.5 M3

YP 2.2.4 (Morty) will be built after 2.5 M3 once the glibc 2.27 issue is fixed

YP 2.4.3 (Rocko) is planned for post YP 2.5.

 

Key YP 2.5 Dates are:

YP 2.5 M3 is in feature freeze.  See status above.

Does this include package updates?

Do we have a place identified for new changes (2.6) while 2.5 stabilizes.

- armin


YP 2.5 M3 was scheduled for release 3/2/18

YP 2.5 M4 cut off of 4/2/18

YP 2.5 M4 release of 4/27/18

 

Tracking Metrics:

            WDD 2673 (last week 2673)

(https://wiki.yoctoproject.org/charts/combo.html)

 

Key Status Links for YP:

https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.5_Status

https://wiki.yoctoproject.org/wiki/Yocto_2.5_Schedule

https://wiki.yoctoproject.org/wiki/Yocto_2.5_Features

 

The Status reports are now stored on the wiki at: https://wiki.yoctoproject.org/wiki/Weekly_Status

 

[If anyone has suggestions for other information you’d like to see on this weekly status update, let us know!]

 

 

Robin Jordan

Yocto Project Program Manager