Current Dev Position: YP 3.1 M1 

Next Deadline: YP 3.1 M1 build Dec. 2, 2019

 

SWAT Team Rotation:

*	SWAT lead is currently: Anuj 
*	SWAT team rotation: Anuj -> Chen on Nov. 15, 2019
*	SWAT team rotation: Chen > Paul on Nov. 22, 2019
*	 <https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team>
https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team

 

Next Team Meetings:

*	Bug Triage meeting Thursday Nov. 14th at 7:30am PDT (
<https://zoom.us/j/454367603> https://zoom.us/j/454367603)
*	Monthly Project Meeting Tuesday Dec. 3rd at 8am PDT (
<https://zoom.us/j/990892712> https://zoom.us/j/990892712)
*	Weekly Engineering Sync Tuesday Nov. 12th at 8am PDT (
<https://zoom.us/j/990892712> https://zoom.us/j/990892712)
*	Twitch - Next event is Tuesday Nov. 12th at 8am PDT (
<https://www.twitch.tv/yocto_project> https://www.twitch.tv/yocto_project)

 

Key Status/Updates:

*	YP 2.7.2 is still undergoing QA
*	There were some key fixes for pseudo related issues which mean it
continues to work with modern distros like Fedora 31.
*	Patches have continued to merge and master is staying roughly
current with the pending patch queue but there continue to be recurring
build failures that are not being addressed.
*	The YP TSC worked on and shared a proposal on how an LTS release
could work which is available at:
<https://docs.google.com/document/d/1AwAFDf52f_FoXksbHEVUMlu4hpcI0JMGVG-Kj_s
Ukyc/>
https://docs.google.com/document/d/1AwAFDf52f_FoXksbHEVUMlu4hpcI0JMGVG-Kj_sU
kyc/ . There has been much discussion about this, patience would be
appreciated as the TSC and governing board work through this to come up with
plans on how we proceed.
*	We are continuing to collect ideas for YP 3.1 in this document:
<https://docs.google.com/document/d/1UKZIGe88-eq3-pOPtkAvFAegbQDzhy_f4ye64yj
nABc/edit?usp=sharing>
https://docs.google.com/document/d/1UKZIGe88-eq3-pOPtkAvFAegbQDzhy_f4ye64yjn
ABc/edit?usp=sharing
*	If anyone has any status items for the project they'd like to add to
the weekly reports, please email Richard and Stephen.

 

Proposed YP 3.1 Milestone Dates:

*	YP 3.1 M1 Proposed build date 12/2/2019
*	YP 3.1 M1 Proposed release date 12/13/2019
*	YP 3.1 M2 Proposed build date 1/20/2020
*	YP 3.1 M2 Proposed release date 1/31/2020
*	YP 3.1 M3 Proposed build date 2/24/2020
*	YP 3.1 M3 Proposed release date 3/6/2020
*	YP 3.1 M4 Proposed build date  3/30/2020
*	YP 3.1 M4 Proposed release date  4/24/2020

 

Planned upcoming dot releases:

*	YP 3.0.1 has patches being queued in poky-contrib
*	YP 2.7.2 (Warrior) is in QA.

 

Tracking Metrics:

*	WDD 2508 (last week 2518) (
<https://wiki.yoctoproject.org/charts/combo.html>
https://wiki.yoctoproject.org/charts/combo.html)
*	Poky Patch Metrics  

*	Total patches found: 1445 (last week 1446)
*	Patches in the Pending State: 579 (40%) [last week 579 (40%)]

 

The Yocto Project's technical governance is through its Technical Steering
Committee, more information is available at:

 <https://wiki.yoctoproject.org/wiki/TSC>
https://wiki.yoctoproject.org/wiki/TSC

 

The Status reports are now stored on the wiki at:
<https://wiki.yoctoproject.org/wiki/Weekly_Status>
https://wiki.yoctoproject.org/wiki/Weekly_Status

 

[If anyone has suggestions for other information you'd like to see on this
weekly status update, let us know!]

 

Thanks,

 

Stephen K. Jolley

Yocto Project Project Manager

*    Cell:                (208) 244-4460

* Email:               <mailto:sjolley.yp.pm@gmail.com>
sjolley.yp.pm@gmail.com

 


[-- Attachment #2: Type: text/html, Size: 26400 bytes --]

^ permalink raw reply	[flat|nested] 5+ messages in thread

* Re: Yocto Project Status WW46'19
  2019-11-12 15:47 Yocto Project Status WW46'19 sjolley.yp.pm
@ 2019-11-15  0:11   ` akuster808
  0 siblings, 0 replies; 5+ messages in thread
From: akuster808 @ 2019-11-15  0:11 UTC (permalink / raw)
  To: sjolley.yp.pm, yocto, openembedded-core

[-- Attachment #1: Type: text/plain, Size: 4016 bytes --]


Hello Stephen,

On 11/12/19 7:47 AM, sjolley.yp.pm@gmail.com wrote:
>
> Current Dev Position: YP 3.1 M1 
>
> Next Deadline: YP 3.1 M1 build Dec. 2, 2019
>
>  
>
> SWAT Team Rotation:
>
>   * SWAT lead is currently: Anuj 
>   * SWAT team rotation: Anuj -> Chen on Nov. 15, 2019
>   * SWAT team rotation: Chen > Paul on Nov. 22, 2019
>   * https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team
>

I watch and triage stable branch builds I initiate week after week and I
no longer want to take on the responsibilities for the other builds. I
therefor am removing my name from the normal swat rotation and have
updated the wiki accordingly.  This should set the appropriate
expectations. This unfortunately puts the full burden back on Intel and
WindRiver.  If things should change in the future, I will let you know.

regards,
Armin

>  *
>
>  
>
> Next Team Meetings:
>
>   * Bug Triage meeting Thursday Nov. 14th at 7:30am PDT
>     (https://zoom.us/j/454367603)
>   * Monthly Project Meeting Tuesday Dec. 3rd at 8am PDT
>     (https://zoom.us/j/990892712) <https://zoom.us/j/990892712>
>   * Weekly Engineering Sync Tuesday Nov. 12th at 8am PDT
>     (https://zoom.us/j/990892712) <https://zoom.us/j/990892712>
>   * Twitch - Next event is Tuesday Nov. 12th at 8am PDT
>     (https://www.twitch.tv/yocto_project)
>
>  
>
> Key Status/Updates:
>
>   * YP 2.7.2 is still undergoing QA
>   * There were some key fixes for pseudo related issues which mean it
>     continues to work with modern distros like Fedora 31.
>   * Patches have continued to merge and master is staying roughly
>     current with the pending patch queue but there continue to be
>     recurring build failures that are not being addressed.
>   * The YP TSC worked on and shared a proposal on how an LTS release
>     could work which is available at:
>     https://docs.google.com/document/d/1AwAFDf52f_FoXksbHEVUMlu4hpcI0JMGVG-Kj_sUkyc/
>     . There has been much discussion about this, patience would be
>     appreciated as the TSC and governing board work through this to
>     come up with plans on how we proceed.
>   * We are continuing to collect ideas for YP 3.1 in this document:
>     https://docs.google.com/document/d/1UKZIGe88-eq3-pOPtkAvFAegbQDzhy_f4ye64yjnABc/edit?usp=sharing
>   * If anyone has any status items for the project they’d like to add
>     to the weekly reports, please email Richard and Stephen.
>
>  
>
> Proposed YP 3.1 Milestone Dates:
>
>   * YP 3.1 M1 Proposed build date 12/2/2019
>   * YP 3.1 M1 Proposed release date 12/13/2019
>   * YP 3.1 M2 Proposed build date 1/20/2020
>   * YP 3.1 M2 Proposed release date 1/31/2020
>   * YP 3.1 M3 Proposed build date 2/24/2020
>   * YP 3.1 M3 Proposed release date 3/6/2020
>   * YP 3.1 M4 Proposed build date  3/30/2020
>   * YP 3.1 M4 Proposed release date  4/24/2020
>
>  
>
> Planned upcoming dot releases:
>
>   * YP 3.0.1 has patches being queued in poky-contrib
>   * YP 2.7.2 (Warrior) is in QA.
>
>  
>
> Tracking Metrics:
>
>   * WDD 2508 (last week
>     2518)(https://wiki.yoctoproject.org/charts/combo.html)
>   * Poky Patch Metrics  
>       o Total patches found: 1445 (last week 1446)
>       o Patches in the Pending State: 579 (40%) [last week 579 (40%)]
>
>  
>
> The Yocto Project’s technical governance is through its Technical
> Steering Committee, more information is available at:
>
> https://wiki.yoctoproject.org/wiki/TSC
>
>  
>
> The Status reports are now stored on the wiki at:
> https://wiki.yoctoproject.org/wiki/Weekly_Status
>
>  
>
> [If anyone has suggestions for other information you’d like to see on
> this weekly status update, let us know!]
>
>  
>
> Thanks,
>
>  
>
> */Stephen K. Jolley/**//*
>
> *Yocto Project Project Manager*
>
> (    *Cell*:                (208) 244-4460
>
> * *Email*:              _sjolley.yp.pm@gmail.com
> <mailto:sjolley.yp.pm@gmail.com>_
>
>  
>
>


[-- Attachment #2: Type: text/html, Size: 31453 bytes --]

^ permalink raw reply	[flat|nested] 5+ messages in thread

* Re: [yocto] Yocto Project Status WW46'19
@ 2019-11-15  0:11   ` akuster808
  0 siblings, 0 replies; 5+ messages in thread
From: akuster808 @ 2019-11-15  0:11 UTC (permalink / raw)
  To: sjolley.yp.pm, yocto, openembedded-core

[-- Attachment #1: Type: text/plain, Size: 4016 bytes --]


Hello Stephen,

On 11/12/19 7:47 AM, sjolley.yp.pm@gmail.com wrote:
>
> Current Dev Position: YP 3.1 M1 
>
> Next Deadline: YP 3.1 M1 build Dec. 2, 2019
>
>  
>
> SWAT Team Rotation:
>
>   * SWAT lead is currently: Anuj 
>   * SWAT team rotation: Anuj -> Chen on Nov. 15, 2019
>   * SWAT team rotation: Chen > Paul on Nov. 22, 2019
>   * https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team
>

I watch and triage stable branch builds I initiate week after week and I
no longer want to take on the responsibilities for the other builds. I
therefor am removing my name from the normal swat rotation and have
updated the wiki accordingly.  This should set the appropriate
expectations. This unfortunately puts the full burden back on Intel and
WindRiver.  If things should change in the future, I will let you know.

regards,
Armin

>  *
>
>  
>
> Next Team Meetings:
>
>   * Bug Triage meeting Thursday Nov. 14th at 7:30am PDT
>     (https://zoom.us/j/454367603)
>   * Monthly Project Meeting Tuesday Dec. 3rd at 8am PDT
>     (https://zoom.us/j/990892712) <https://zoom.us/j/990892712>
>   * Weekly Engineering Sync Tuesday Nov. 12th at 8am PDT
>     (https://zoom.us/j/990892712) <https://zoom.us/j/990892712>
>   * Twitch - Next event is Tuesday Nov. 12th at 8am PDT
>     (https://www.twitch.tv/yocto_project)
>
>  
>
> Key Status/Updates:
>
>   * YP 2.7.2 is still undergoing QA
>   * There were some key fixes for pseudo related issues which mean it
>     continues to work with modern distros like Fedora 31.
>   * Patches have continued to merge and master is staying roughly
>     current with the pending patch queue but there continue to be
>     recurring build failures that are not being addressed.
>   * The YP TSC worked on and shared a proposal on how an LTS release
>     could work which is available at:
>     https://docs.google.com/document/d/1AwAFDf52f_FoXksbHEVUMlu4hpcI0JMGVG-Kj_sUkyc/
>     . There has been much discussion about this, patience would be
>     appreciated as the TSC and governing board work through this to
>     come up with plans on how we proceed.
>   * We are continuing to collect ideas for YP 3.1 in this document:
>     https://docs.google.com/document/d/1UKZIGe88-eq3-pOPtkAvFAegbQDzhy_f4ye64yjnABc/edit?usp=sharing
>   * If anyone has any status items for the project they’d like to add
>     to the weekly reports, please email Richard and Stephen.
>
>  
>
> Proposed YP 3.1 Milestone Dates:
>
>   * YP 3.1 M1 Proposed build date 12/2/2019
>   * YP 3.1 M1 Proposed release date 12/13/2019
>   * YP 3.1 M2 Proposed build date 1/20/2020
>   * YP 3.1 M2 Proposed release date 1/31/2020
>   * YP 3.1 M3 Proposed build date 2/24/2020
>   * YP 3.1 M3 Proposed release date 3/6/2020
>   * YP 3.1 M4 Proposed build date  3/30/2020
>   * YP 3.1 M4 Proposed release date  4/24/2020
>
>  
>
> Planned upcoming dot releases:
>
>   * YP 3.0.1 has patches being queued in poky-contrib
>   * YP 2.7.2 (Warrior) is in QA.
>
>  
>
> Tracking Metrics:
>
>   * WDD 2508 (last week
>     2518)(https://wiki.yoctoproject.org/charts/combo.html)
>   * Poky Patch Metrics  
>       o Total patches found: 1445 (last week 1446)
>       o Patches in the Pending State: 579 (40%) [last week 579 (40%)]
>
>  
>
> The Yocto Project’s technical governance is through its Technical
> Steering Committee, more information is available at:
>
> https://wiki.yoctoproject.org/wiki/TSC
>
>  
>
> The Status reports are now stored on the wiki at:
> https://wiki.yoctoproject.org/wiki/Weekly_Status
>
>  
>
> [If anyone has suggestions for other information you’d like to see on
> this weekly status update, let us know!]
>
>  
>
> Thanks,
>
>  
>
> */Stephen K. Jolley/**//*
>
> *Yocto Project Project Manager*
>
> (    *Cell*:                (208) 244-4460
>
> * *Email*:              _sjolley.yp.pm@gmail.com
> <mailto:sjolley.yp.pm@gmail.com>_
>
>  
>
>


[-- Attachment #2: Type: text/html, Size: 31453 bytes --]

^ permalink raw reply	[flat|nested] 5+ messages in thread

* Re: [OE-core] Yocto Project Status WW46'19
  2019-11-15  0:11   ` [yocto] " akuster808
@ 2019-11-15  0:17     ` Richard Purdie
  -1 siblings, 0 replies; 5+ messages in thread
From: Richard Purdie @ 2019-11-15  0:17 UTC (permalink / raw)
  To: akuster808, sjolley.yp.pm, yocto, openembedded-core, Erway,
	Tracey M, Ross Burton

On Thu, 2019-11-14 at 16:11 -0800, akuster808 wrote:
> 
> Hello Stephen,
> 
> On 11/12/19 7:47 AM, sjolley.yp.pm@gmail.com wrote:
> > Current Dev Position: YP 3.1 M1 
> > Next Deadline: YP 3.1 M1 build Dec. 2, 2019
> >  
> > SWAT Team Rotation:
> > SWAT lead is currently: Anuj 
> > SWAT team rotation: Anuj -> Chen on Nov. 15, 2019
> > SWAT team rotation: Chen > Paul on Nov. 22, 2019
> > https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team
>  
> I watch and triage stable branch builds I initiate week after week
> and I no longer want to take on the responsibilities for the other
> builds. I therefor am removing my name from the normal swat rotation
> and have updated the wiki accordingly.  This should set the
> appropriate expectations. This unfortunately puts the full burden
> back on Intel and WindRiver.  If things should change in the future,
> I will let you know.

Thanks for your work on that team, its been hugely appreciated. 

I think it may be time that we suspend the SWAT process and have the
build owners handle it themselves.

Cheers,

Richard



^ permalink raw reply	[flat|nested] 5+ messages in thread

* Re: [yocto] Yocto Project Status WW46'19
@ 2019-11-15  0:17     ` Richard Purdie
  0 siblings, 0 replies; 5+ messages in thread
From: Richard Purdie @ 2019-11-15  0:17 UTC (permalink / raw)
  To: akuster808, sjolley.yp.pm, yocto, openembedded-core, Erway,
	Tracey M, Ross Burton

On Thu, 2019-11-14 at 16:11 -0800, akuster808 wrote:
> 
> Hello Stephen,
> 
> On 11/12/19 7:47 AM, sjolley.yp.pm@gmail.com wrote:
> > Current Dev Position: YP 3.1 M1 
> > Next Deadline: YP 3.1 M1 build Dec. 2, 2019
> >  
> > SWAT Team Rotation:
> > SWAT lead is currently: Anuj 
> > SWAT team rotation: Anuj -> Chen on Nov. 15, 2019
> > SWAT team rotation: Chen > Paul on Nov. 22, 2019
> > https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team
>  
> I watch and triage stable branch builds I initiate week after week
> and I no longer want to take on the responsibilities for the other
> builds. I therefor am removing my name from the normal swat rotation
> and have updated the wiki accordingly.  This should set the
> appropriate expectations. This unfortunately puts the full burden
> back on Intel and WindRiver.  If things should change in the future,
> I will let you know.

Thanks for your work on that team, its been hugely appreciated. 

I think it may be time that we suspend the SWAT process and have the
build owners handle it themselves.

Cheers,

Richard



^ permalink raw reply	[flat|nested] 5+ messages in thread

end of thread, other threads:[~2019-11-15  0:17 UTC | newest]

Thread overview: 5+ messages (download: mbox.gz / follow: Atom feed)
-- links below jump to the message on this page --
2019-11-12 15:47 Yocto Project Status WW46'19 sjolley.yp.pm
2019-11-15  0:11 ` akuster808
2019-11-15  0:11   ` [yocto] " akuster808
2019-11-15  0:17   ` [OE-core] " Richard Purdie
2019-11-15  0:17     ` [yocto] " Richard Purdie

This is an external index of several public inboxes,
see mirroring instructions on how to clone and mirror
all data and code used by this external index.