* Yocto Project Status WW47
@ 2016-11-18 16:35 Jolley, Stephen K
2016-11-18 18:54 ` akuster
0 siblings, 1 reply; 3+ messages in thread
From: Jolley, Stephen K @ 2016-11-18 16:35 UTC (permalink / raw)
To: yocto, openembedded-core
[-- Attachment #1: Type: text/plain, Size: 2419 bytes --]
Current Dev Position: YP 2.3 M1
Next Deadline: YP 2.3 M1 by Dec. 12, 2016
SWAT team rotation: Leo -> Juro
https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team
Key Status/Updates:
* 2.1.2 QA report is out and likely to be released imminently.
* The QA report for 2.1.2 is at: https://wiki.yoctoproject.org/wiki/WW46_-_2016-11-10_-_Test_Cycle_2.1.2_rc1
* At this point most 2.3 targeted features should have been identified in bugzilla. M1 is comparatively loaded compared to M2/M3 and some individuals have particularly heavy workloads so loading balancing is being done.
* We'll run a 2.0.3 test build over the weekend to find out our status there.
* Backports of fixes to the morty release branch are now occurring, thanks Armin. Armin is looking like the principle morty maintainer for that stable release series.
* There are some changes planned to the getVar/getVarFlag expansion defaults and the old data store APIs are likely to be removed imminently. There is an email on the openembedded-architecture list about this.
* WDD is now climbing again unfortunately, we've wiped out half of the improvements we made in the 2.2 cycle.
Proposed upcoming dot releases:
YP 2.0.3 Release by Dec. 9, 2016
YP 2.2.1 Release by Jan. 20, 2017
YP 2.1.3 Release by May. 19, 2017
Key YP 2.3 Dates:
YP 2.3 M1 Cutoff is Dec. 12, 2016
YP 2.3 M1 Release is Dec. 23, 2016
YP 2.3 M2 Cutoff is Jan. 23, 2017
YP 2.3 M2 Release is Feb. 3, 2017
YP 2.3 M3 Cutoff is Feb 27, 2017
YP 2.3 M3 Release is Mar. 10, 2017
YP 2.3 M4 Cutoff is April 3, 2017
YP 2.3 M4 Release is April 28, 2017
Tracking Metrics:
WDD 2516 (last week 2497)
(https://wiki.yoctoproject.org/charts/combo.html)
Key Status Links for YP:
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.3_Status
https://wiki.yoctoproject.org/wiki/Yocto_2.3_Schedule
https://wiki.yoctoproject.org/wiki/Yocto_2.3_Features
[If anyone has suggestions for other information you'd like to see on this weekly status update, let us know!]
Thanks,
Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
* Work Telephone: (503) 712-0534
* Cell: (208) 244-4460
* Email: stephen.k.jolley@intel.com
[-- Attachment #2: Type: text/html, Size: 20182 bytes --]
^ permalink raw reply [flat|nested] 3+ messages in thread
* Re: Yocto Project Status WW47
2016-11-18 16:35 Yocto Project Status WW47 Jolley, Stephen K
@ 2016-11-18 18:54 ` akuster
0 siblings, 0 replies; 3+ messages in thread
From: akuster @ 2016-11-18 18:54 UTC (permalink / raw)
To: Jolley, Stephen K, yocto, openembedded-core
[-- Attachment #1: Type: text/plain, Size: 2804 bytes --]
Stephen
On 11/18/2016 08:35 AM, Jolley, Stephen K wrote:
>
> Current Dev Position: YP 2.3 M1
>
> Next Deadline: YP 2.3 M1 by Dec. 12, 2016
>
> SWAT team rotation: Leo -> Juro
>
> https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team
>
> Key Status/Updates:
>
Thanks for the updates.
> ·2.1.2 QA report is out and likely to be released imminently.
>
> ·The QA report for 2.1.2 is at:
> https://wiki.yoctoproject.org/wiki/WW46_-_2016-11-10_-_Test_Cycle_2.1.2_rc1
>
> ·At this point most 2.3 targeted features should have been identified
> in bugzilla. M1 is comparatively loaded compared to M2/M3 and some
> individuals have particularly heavy workloads so loading balancing is
> being done.
>
> ·We’ll run a 2.0.3 test build over the weekend to find out our status
> there.
>
> ·Backports of fixes to the morty release branch are now occurring,
> thanks Armin. Armin is looking like the principle morty maintainer for
> that stable release series.
>
> ·There are some changes planned to the getVar/getVarFlag expansion
> defaults and the old data store APIs are likely to be removed
> imminently. There is an email on the openembedded-architecture list
> about this.
>
> ·WDD is now climbing again unfortunately, we’ve wiped out half of the
> improvements we made in the 2.2 cycle.
>
> Proposed upcoming dot releases:
>
> YP 2.0.3 Release by Dec. 9, 2016
>
> YP 2.2.1 Release by Jan. 20, 2017
>
> YP 2.1.3 Release by May. 19, 2017
>
Would it be reasonable to target a "Code freeze/cutoff" (ie last day to
accept patch for any of those dot releases) the week before or more to
give Maintainers time to merge and run a test build(s)?
- Armin
> Key YP 2.3 Dates:
>
> YP 2.3 M1 Cutoff is Dec. 12, 2016
>
> YP 2.3 M1 Release is Dec. 23, 2016
>
> YP 2.3 M2 Cutoff is Jan. 23, 2017
>
> YP 2.3 M2 Release is Feb. 3, 2017
>
> YP 2.3 M3 Cutoff is Feb 27, 2017
>
> YP 2.3 M3 Release is Mar. 10, 2017
>
> YP 2.3 M4 Cutoff is April 3, 2017
>
> YP 2.3 M4 Release is April 28, 2017
>
> Tracking Metrics:
>
> WDD 2516 (last week 2497)
>
> (https://wiki.yoctoproject.org/charts/combo.html)
>
> Key Status Links for YP:
>
> https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.3_Status
>
> https://wiki.yoctoproject.org/wiki/Yocto_2.3_Schedule
>
> https://wiki.yoctoproject.org/wiki/Yocto_2.3_Features
>
> [If anyone has suggestions for other information you’d like to see on
> this weekly status update, let us know!]
>
> Thanks,
>
> */Stephen K. Jolley/**//*
>
> *Yocto Project Program Manager*
>
> *INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124 *
>
> (*Work Telephone*: (503) 712-0534
>
> (*Cell*: (208) 244-4460
>
> * *Email*:_stephen.k.jolley@intel.com_
>
>
>
[-- Attachment #2: Type: text/html, Size: 23099 bytes --]
^ permalink raw reply [flat|nested] 3+ messages in thread
* Yocto Project Status WW47
@ 2015-11-20 16:13 Jolley, Stephen K
0 siblings, 0 replies; 3+ messages in thread
From: Jolley, Stephen K @ 2015-11-20 16:13 UTC (permalink / raw)
To: yocto, openembedded-core
[-- Attachment #1: Type: text/plain, Size: 1634 bytes --]
Current Dev Position: YP 2.1 M1
Next Deadline: YP 2.1 M1 Cutoff December 7, 2015 noon GMT
SWAT team rotation: Jussi -> Alejandro
https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team
Key Status/Updates:
* YP 2.1 Planning is nearing completion.
* Patches continuing to merge into master to start 2.1 development process
Key YP 2.1 Dates:
YP 2.1 M1 Cutoff (Feature Freeze) date is December 7, 2015 noon GMT
YP 2.1 M1 Target release date is December 24, 2015
YP 2.1 M2 Cutoff (Feature Freeze) date is January 25, 2016 noon GMT
YP 2.1 M2 Target release date is February 12, 2016
YP 2.1 M3 Cutoff (Feature Freeze) date is February 29, 2016 noon GMT
YP 2.1 M3 Target release date is March 18, 2016
YP 2.1 M4 / Final Cutoff: March 28, 2016 noon GMT - Stabilization only milestone.
YP 2.1 Final Release Target: April 29, 2016
Key Status Links for YP:
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.1_Status
https://wiki.yoctoproject.org/wiki/Yocto_2.1_Schedule
https://wiki.yoctoproject.org/wiki/Yocto_2.1_Features
Tracking Metrics:
WDD 2162 (last week 2181)
(https://wiki.yoctoproject.org/charts/combo.html)
[If anyone has suggestions for other information you'd like to see on this weekly status update, let us know!]
Thanks,
Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
* Work Telephone: (503) 712-0534
* Cell: (208) 244-4460
* Email: stephen.k.jolley@intel.com
[-- Attachment #2: Type: text/html, Size: 17591 bytes --]
^ permalink raw reply [flat|nested] 3+ messages in thread
end of thread, other threads:[~2016-11-18 18:54 UTC | newest]
Thread overview: 3+ messages (download: mbox.gz / follow: Atom feed)
-- links below jump to the message on this page --
2016-11-18 16:35 Yocto Project Status WW47 Jolley, Stephen K
2016-11-18 18:54 ` akuster
-- strict thread matches above, loose matches on Subject: below --
2015-11-20 16:13 Jolley, Stephen K
This is an external index of several public inboxes,
see mirroring instructions on how to clone and mirror
all data and code used by this external index.